Project changes result from three basic causes.Which of the following is not one of those causes?
A) Uncertainty about the technology on which the work of the project or its output is based
B) An increase in the knowledge base or sophistication of the client / user leading to scope creep
C) Changes to the environment in which the project is being completed
D) A modification of the rules applying to the process of carrying out the project or to its output
Correct Answer:
Verified
Q20: The two fundamental objectives of control are
Q21: The critical ratio control chart uses a
Q22: Because project milestones may not occur at
Q23: The _ process controls the project at
Q24: The _ is calculated as (actual progress
Q26: _ are seen as much the same
Q27: Change control systems,in some industries,are part of
Q28: PMBOK recognizes the importance of what is
Q29: _ is a management approach that may
Q30: Postproject controls or reviews are examples of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents