The process design team at a manufacturer has broken an assembly process into eight basic steps,each with a required time,and predecessor as shown in the table.They work a 7 hour day and want to produce at a rate of 360 units per day.What should their takt time be?
A) 70 seconds
B) 65 seconds
C) 52 seconds
D) 25 seconds
Correct Answer:
Verified
Q22: Products that are customized only at the
Q40: Draw the product-process matrix and discuss the
Q45: Champion Cooling has just signed a contract
Q46: In a service blueprint, the two layers
Q49: As the degree of customer contact decreases,more
Q67: Use this scenario for the following
Q78: Define the terms front room and back
Q80: Use this scenario for the following
Q82: A manager deciding where six departments could
Q98: Cycle time is the sum of all
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents