There are 200 units in inventory at the start of week 1.What are the net requirements in week 4 if there is a scheduled receipt of 100 units every other week and a two week production lead time? 
A) 250
B) 300
C) 350
D) 400
Correct Answer:
Verified
Q48: Cow Company used the master schedule to
Q51: There is no beginning inventory.What are the
Q52: Using this MRP record and a lead
Q54: There are 50 units in inventory at
Q55: Consider the product structure tree shown below:
Q56: A mechanical cat is made of two
Q56: The process of _ occurs when a
Q58: An MRP system cannot answer the question:
A)"how
Q58: A mechanical cat is made of two
Q65: In material requirements planning, units already on