A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project takes more than 34 days?
A) 0.788
B) 0.212
C) 0.945
D) 0.055
Correct Answer:
Verified
Q78: Q79: Q79: Q80: Use the information in the table Q81: A project has the precedence requirements Q83: Use the values in the table Q84: Activity float is the difference between the Q85: One approach to reducing project length would Q86: The PERT technique assumes that durations are Q87: Float is always measured in exactly the Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents