Question 24

Multiple Choice

It's resource leveling time at Satriale's Pork Store and management is pondering four possibilities for task splitting.Which of these activities would be the worst candidate for splitting?


A) Silvio's task,which requires several workers
B) Paulie's task,which is the most expensive
C) Richie's task,which has high start-up costs
D) Ralph's task,which is the least expensive

Correct Answer: