Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day) to this project.Assume that the project work is conducted on a 5-day-per-week basis.
A) 5 hours
B) 10 hours
C) 4 hours
D) 8 hours
Correct Answer:
Verified