A Project Consisting of Six Activities Is Shown in the Table.The

Question 63

Multiple Choice

A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs:  Activity  Duration (days)   Activity Cost  Predecessor K10140L864 K,MM1296N6120MP14168 LQ12144 N\begin{array} { | l | l | l | l | } \hline \text { Activity } & \text { Duration (days) } & \text { Activity Cost } & \text { Predecessor } \\\hline \mathrm { K } & 10 & 140 & \\\hline \mathrm { L } & 8 & 64 & \mathrm {~K} , \mathrm { M } \\\hline \mathrm { M } & 12 & 96 & \\\hline \mathrm { N } & 6 & 120 & \mathrm { M } \\\hline \mathrm { P } & 14 & 168 & \mathrm {~L} \\\hline \mathrm { Q } & 12 & 144 & \mathrm {~N} \\\hline\end{array}


A) On days 19 through 20 for an early start schedule.
B) On days 17 through 20 for a late start schedule.
C) On days 13 through 18 for an early start schedule.
D) On days 21 through 22 for a late start schedule.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents