Solved

Skyline Builders and Pine Lumber Had a Contract, Calling for Pine

Question 19

Multiple Choice

Skyline Builders and Pine Lumber had a contract, calling for Pine Lumber to deliver a certain quantity of bricks to Skyline's place of business on the first of every month for one year. Pine delivered the bricks one week late for the first six months, but Skyline did not object. When Pine delivered the bricks one week late, as usual, in the seventh month, Skyline attempted to cancel the contract because of the late delivery. Which of the following is true about this scenario?


A) Pine will have to return the delivery fee of the first six months because it broke the contract.
B) Skyline does not have the legal right to modify the contract.
C) Pine is not in breach because the delivery was made at the intended place of business.
D) Skyline has waived its right to cancel the contract.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents