Assume a project has normal cash flows.Given this,you should accept the project
A) if,and only if,the NPV is exactly equal to zero.
B) only if the NPV is equal to the initial cash flow.
C) if the NPV is positive and reject it if the NPV is negative.
D) if the total cash inflows exceed the initial cash outflow.
E) because it has positive cash flows for every time period after the initial investment.
Correct Answer:
Verified
Q5: The payback method
A)discounts all cash flows properly.
B)requires
Q7: All else equal,the payback period for a
Q9: What is the key reason why a
Q10: The length of time required for an
Q12: An investment
A)is acceptable if its calculated payback
Q12: What is the primary shortcoming of the
Q14: Net present value
A)considers only cash flows occurring
Q17: An investment is acceptable if its average
Q17: A project has a net present value
Q18: The payback method is a convenient and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents