A project is expected to produce cash flows of $12,800,$15,900,and $18,000 over the next 3 years,respectively.After 3 years,the project will be discontinued.What is this project worth today at a discount rate of 12.5 percent?
A) $35,201.76
B) $34,435.74
C) $36,582.72
D) $36,808.17
E) $35,758.00
Correct Answer:
Verified