Question 137

Multiple Choice

Which one of the following standard cost variances is not available when analyzing batch-related manufacturing overhead costs using an activity-based cost (ABC) system?


A) Production-volume variance.
B) Variable setup spending variance.
C) Fixed spending variance.
D) Fixed flexible-budget variance.
E) Sales volume variance.

Correct Answer: