A material requirements planning system is an example of which of the following scheduling systems?
A) Infinite loading, backward scheduling
B) Finite loading, backward scheduling
C) Infinite loading, forward scheduling
D) Finite loading, forward scheduling
E) None of these
Correct Answer:
Verified