Here are the data for a time-cost CPM scheduling analysis.The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by four days, what is the total time of the project and total cost?
A) Total time is 10 days, total cost is $2,500.
B) Total time is 9 days, total cost is $2,300.
C) Total time is 8 days, total cost is $2,750.
D) Total time is 8 days, total cost is $1,850.
E) Total time is 9 days, total cost is $2,350.
Correct Answer:
Verified
Q63: In CPM analysis, it is generally expected
Q66: What do the initials EVM stand for?
Q67: You have just performed a CPM analysis
Q67: You have collected the data for a
Q68: You know when you have arrived at
Q70: What are "project milestones?" _
Q72: Here are the data for a time-cost
Q73: What is that sequence of activities that
Q75: Here are the data for a time-cost
Q76: Describe how CPM handles the trade-offs between
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents