Question 11

Multiple Choice

The second step in the project control process of the measurement and evaluation of project performance is to:


A) Review the baseline plan with top management
B) Analyze inputs to control system
C) Compare plan against actual
D) Measure progress and performance
E) Review spending with team members

Correct Answer: