To Calculate a Project's Net Present Value (NPV),the Project's Required

Question 5

Multiple Choice

To calculate a project's net present value (NPV) ,the project's required rate of return is used to:


A) compound cash flows to their future values.
B) convert future cash flows to their equivalent values today.
C) compute the weighted average cost of capital to discount the cash flows.
D) convert the non-operating cash flows into operating cash flows.

Correct Answer:

verifed

Verified