The Rule for Project Acceptance Under the Net-Present-Value Method Is

Question 23

Multiple Choice

The rule for project acceptance under the net-present-value method is that:


A) NPV should be greater than zero.
B) NPV should be less than zero.
C) NPV should equal zero.
D) NPV should be less than the hurdle rate.
E) NPV should equal the hurdle ratE.