Cantor's has been busy analyzing a new product. Thus far, management has determined that an OCF of $218,200 will result in a zero net present value for the project, which is the minimum requirement for project acceptance. The fixed costs are $329,000 and the contribution margin per unit is $216.40. The company feels that it can realistically capture 2.5 percent of the 110,000 unit market for this product. The tax rate is 34 percent and the required rate of return is 11 percent. Should the company develop the new product? Why or why not?
A) Yes; The project's expected IRR exceeds the required rate of return.
B) Yes; The expected level of sales exceeds the required level of production.
C) No; The required level of production exceeds the expected level of sales.
D) No; The IRR is less than the required rate of return.
E) No; The project will never payback on a discounted basis.
Correct Answer:
Verified
Q87: Tucker's Trucking is considering a project with
Q88: A proposed project has a contribution margin
Q89: You are the manager of a project
Q91: Steele Insulators is analyzing a new type
Q91: At an output level of 50,000 units,you
Q95: We are evaluating a project that
Q96: Mountain Gear can manufacture mountain climbing shoes
Q101: Mr.Bear,your boss,will only agree to accept a
Q103: What is forecasting risk and why is
Q106: What are the key features of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents