For an Attributes Sampling Plan, the Tolerable Deviation Rate Is

Question 49

Multiple Choice

For an attributes sampling plan, the tolerable deviation rate is 4%, the computed upper deviation rate is 7%, the sample deviation rate is 3%, and the risk of assessing control risk too low is 5%. Which of the following is true?


A) The auditor must increase control risk because the risk of assessing control risk too low is greater than the tolerable deviation rate.
B) The auditor is likely to increase control risk because the risk of assessing control risk too low is greater than the tolerable deviation rate.
C) The auditor must increase control risk because the computed upper deviation rate is greater than the tolerable deviation rate.
D) The auditor is likely to increase control risk because the computed upper deviation rate is greater than the tolerable deviation rate.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents