Which of the following statements is true concerning the adoption of rolling wave planning in project management?
A) It is facilitated when the second level of the work breakdown structure is organized by phase or design components.
B) It is initially cumbersome,often delaying a prompt and timely project start.
C) It often creates a situation known as "analysis paralysis."
D) It requires detailed bottom-up estimating for every WBS component
Correct Answer:
Verified
Q24: The approved version of a work product
Q24: The Work Breakdown Structure (WBS)is a framework
Q25: Which of the following items best describes
Q25: The project scope planning processes include all
Q26: The approved set of procedures that describe
Q27: All of the following conventions are widely
Q28: Which of the following is not a
Q30: Once the project is underway,each potential change
Q31: Work Breakdown Structures typically include one or
Q40: Which of the following statements concerning work
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents