PERT refers to the Program Evaluation and Review Technique,which was developed in the 1950s to better understand how variability in the duration of individual activity durations impacts the entire project schedule.
Correct Answer:
Verified
Q1: The critical path is the sequence of
Q2: When developing a project schedule,total float (or
Q5: The length of time to perform an
Q5: While the lowest level of decomposition in
Q7: The enumeration method of determining the critical
Q8: A mandatory dependency in a relationship that
Q10: A successor activity follows a predecessor activity
Q11: A Gantt chart is an easy-to-understand tool
Q17: Except in rare circumstances,project teams should not
Q19: The first process in developing a project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents