Pearce Company
Pearce Company uses a standard cost system for its production process.Pearce Company applies overhead based on direct labor hours.The following information is available for July:
Standard: | |
DLH per unit | 2.20 |
Variable overhead per DLH | $2.50 |
Fixed overhead per DLH | |
Budgeted variable overhead | $3.00 |
(based on 11,990 DLHs) |
Actual: | |
Units produced | 4,400 |
Direct labor hours | 8,800 |
Variable overhead | $29,950 |
Fixed overhead | $42,300 |
Refer to Pearce Company Using the three-variance approach,what is the efficiency variance?
A) $11,770 F
B) $2,200 F
C) $7,975 U
D) $5,775 U
Correct Answer:
Verified
Q158: Jenkins Manufacturing
The following information is available
Q159: Buckingham Company
Buckingham Company uses a standard cost
Q160: Commodore Company
Commodore Company uses a standard cost
Q161: Commodore Company
Commodore Company uses a standard cost
Q162: Commodore Company
Commodore Company uses a standard cost
Q164: Pearce Company
Pearce Company uses a standard cost
Q165: Commodore Company
Commodore Company uses a standard cost
Q166: Pearce Company
Pearce Company uses a standard cost
Q167: Pearce Company
Pearce Company uses a standard cost
Q168: Commodore Company
Commodore Company uses a standard cost
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents