Taylor is writing a progress report on development of a new software program for a client.She and her team faced a technical glitch last week which however,has been solved now.Which of the following is the best way to present this information to the client?
A) "I'm really sorry, but we're running 2 days behind schedule. We will however be back on schedule by the end of the month."
B) "We have had a major problem last week because of which our work is affected to an extent. However, we should be able to finish by the due date."
C) "We overcame a major technical glitch last week. We are now on track and expect to finish the work by the due date."
D) "After correcting the huge problem we had last week, we should be back on track by due date if we face no other glitches."
E) "Please accept our sincere apologies. We will be unable to complete the work according to the estimated deadline."
Correct Answer:
Verified
Q54: Lee is researching for a project titled,"Harmful
Q55: Daniel Perez is writing a proposal on
Q56: Which of the following needs to be
Q57: Which of the following questions does the
Q58: Joshua Baker,who works for a telecom company,recently
Q60: Isabella has completed writing a chronological progress
Q61: What are some of the questions that
Q61: What is the best way to organize
Q62: What are the sections that a proposal
Q63: Explain with an example,the work schedule section
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents