A carpenter hammers nails each day at work.In each of the first three hours 50 nails were hammered and the marginal product of the fourth and fifth hours of work is 40 and 20 nails,respectively.Diminishing returns will be experienced in the _____ hour.
A) second
B) third
C) fourth
D) first
Correct Answer:
Verified