Which of the following will not allow for an anticipatory repudiation to occur?
A) Tom calls Dick and says that he can't find the raw materials to complete performance and doubts he can meet the contract's performance deadline
B) Sally is buying Jane's car with the money and car to be exchanged in a week, however, Sally sees Betty who tells her she just bought Jane's car
C) Mary Beth is scheduled for knee surgery next month with Dr. Slice but reads in the paper that Dr. Slice has lost his license to practice medicine
D) Manny calls Moe and tells him that the sculpture he's creating for him is coming along slower than anticipated but he's pretty sure he'll be done by the contract deadline
Correct Answer:
Verified
Q42: In Mobil Oil Exploration & Producing Southeast,Inc.v.United
Q42: Harry sees an AK-47 automatic assault rifle
Q43: Lon has just come home from serving
Q44: Toy Tech (TT)has ordered 50,000 aluminum widgets
Q46: Alan has accepted a new job.Which of
Q48: Sharon has contracted with Craig to buy
Q49: In a delegation situation,the non-delegating party is
Q49: Pete has been fired from his job
Q50: Max has contracted with Lew to have
Q52: Sam has contracted with Dave to purchase
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents