In the 1:10:100 Rule, which of the following would be correct?
A) If a defect or service error is identified and corrected at the design stage, it might cost $100 to fix.
B) If a defect or service error is identified and corrected at the production process stage, it might cost $100 to fix.
C) If a defect or service error is identified and corrected after it reaches the customer, it might cost $100 to fix.
D) If a defect or service error is identified and corrected at the design stage, it might cost $1 * $10 * $100 = $1,000 to fix.
Correct Answer:
Verified
Q1: Quality control focuses on the design of
Q30: Testing whether a computer boots up the
Q31: Evaluating the trade-offs between the costs of
Q32: Which of the following is most closely
Q40: Common cause variation
A)Cannot be explained except in
Q41: In manufacturing, quality control is generally applied
Q45: With good management, all variability of output
Q75: Larger sample sizes allow smaller changes in
Q76: The lower the rate of defects, the
Q78: A system governed only by common causes
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents