The Vito Company makes tables for which the following standards have been developed: Production of 200 tables was expected in July,but 220 tables were actually completed.Direct materials purchased and used were 2,000 pounds at an actual price of $4.40 per pound.Direct labor cost for the month was $10,620,and the actual pay per hour was $18.00.What is the direct material quantity variance for July?
A) $800 Favorable
B) $800 Unfavorable
C) $880 Favorable
D) $880 Unfavorable
Correct Answer:
Verified
Q62: Currently attainable standards are levels of performance
Q66: Currently attainable standards do not make allowances
Q75: Sales-activity variances measure how efficient managers have
Q88: Rate variances are the same as _
Q100: An expected cost is the cost that
Q102: The Patriot Company makes chairs for which
Q103: The Long Company makes tables for which
Q104: Borabora Company produces 2,500 units.Each unit was
Q105: The following information is for Euclid Corporation:
Q106: The following information is for Kickapoo Corporation:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents