The First Step in Developing an ABC System Is

Question 68

Multiple Choice

The first step in developing an ABC system is


A) calculate an activity cost allocation rate for each activity.
B) allocate the costs to the cost object using the activity cost allocation rates.
C) select an allocation base for each activity.
D) identify the primary activities and estimate a total cost pool for each.

Correct Answer:

verifed

Verified