On-time performance is
A) the time it takes distribution to pick up an order and deliver it to the customer.
B) within 2 standard deviations of customer response time.
C) within 2 standard deviations of manufacturing time.
D) equal to customer response time, divided by the number of orders from a specific customer.
E) when the product is delivered at the time scheduled to be delivered.
Correct Answer:
Verified
Q115: Manufacturing lead time includes
A)all indirect time.
B)waiting time.
C)marketing
Q117: For a fast-food restaurant the average waiting
Q118: The demand for Ballard's Glass Company's products
Q118: Manufacturing lead time is the sum of
Q119: The demand for Ballard's Glass Company's products
Q121: The costs relating to product testing are
Q123: Sof-T, Inc.manufactures foam products for upholstery companies.It
Q124: Adventure Gear Ltd.manufactures a self inflatable mattress
Q125: Answer the following question(s)using the information below:
The
Q130: Brown Laundry has a variable demand. The
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents