Construction of the Cattery Could Be Distilled to Eight Distinct

Question 54

Essay

Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.
 Activity  Predecessors  Time (weeks)  A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

Correct Answer:

verifed

Verified

\[\begin{array} { | c | c | c | c | c | ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents