Highrise Constructions Ltd had a large 3-year project with total revenue of $5 000 000 and estimated total costs of $4 200 000. The project was 25% complete at the end of the first year, 55% complete at the end of the second year, and 100% complete at the end of the third year. Revenues and costs were as estimated.
-What profit was earned during the second year if the percentage of completion method was used?


A) $200 000
B) $240 000
C) $440 000
D) $1 500 000.