On January 4th,Stevens Manufacturing Received an Order for 30 Uniforms

Question 137

Multiple Choice

On January 4th,Stevens Manufacturing received an order for 30 uniforms.The following information pertained to that order. Hours Required
Receive and process order 0.25
Waiting for production to begin 1.25
Cutting 50.00
Sewing and lettering 300.00
Moving materials from one station to another 20.00
Waiting for an operation to begin 95.00
Packaging 35.00
Loading to be shipped 0.50
In transit to customer 5.00
Calculate the manufacturing cycle efficiency.


A) 70%
B) 60%
C) 69%
D) 10%