On January 4th,Stevens Manufacturing received an order for 30 uniforms.The following information pertained to that order. Hours Required
Receive and process order 0.25
Waiting for production to begin 1.25
Cutting 50.00
Sewing and lettering 300.00
Moving materials from one station to another 20.00
Waiting for an operation to begin 95.00
Packaging 35.00
Loading to be shipped 0.50
In transit to customer 5.00
Calculate the manufacturing cycle efficiency.
A) 70%
B) 60%
C) 69%
D) 10%
Correct Answer:
Verified
Q121: Which of the following organizations would benefit
Q132: The goal of benchmarking is to
A)Identify those
Q133: From a customer's perspective,the time lapse between
Q134: On January 4th,Stevens Manufacturing received an order
Q135: The time from the start of a
Q136: A balanced scorecard should include five to
Q139: A balanced scorecard should include five to
Q140: If a public utility company wanted to
Q142: Midland Industries is the manufacturer of metal-frame
Q153: Budget Taxi Service operates a transportation service
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents