Andrew Pallet Co., Inc.manufactures pallets for various manufacturing companies.Each new employee takes 10 hours to make the first pallet and 8 hours to make the second.The manufacturing overhead charge per hour is $80.Required:
a.What is the learning curve percentage assuming the cumulative average method?
b.What is the time needed to build 8 pallets by a new employee using the cumulative average-time method? Assume the rate of learning factor is -0.1520.
c.What is the time needed to produce the 16th pallet by a new employee using the incremental unit-time method? Assume the rate of learning factor is -0.3219.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q141: The incremental unit-time learning model with a
Q146: When new products are introduced, learning-curve effects
Q150: Plotting learning curve observations is helpful in
Q157: A learning curve measures the effect of
Q236: Schotte Manufacturing Company uses two different independent
Q242: A learning curve is a function
A)that measures
Q243: Each time Maiertree Care hires a new
Q244: Vestor Ltd.has estimated a 90% incremental unit
Q245: When an average unit of time declines
Q246: Vestor Ltd.has estimated a 90% cumulative average-time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents