Quick Shop Printing has two workstations, cutting and pasting. The cutting station is limited by the speed of operating the cutting machine. Pasting is limited by the speed of the workers. Pasting normally waits on work from cutting. Each department works an eight-hour day. If cutting begins work two hours earlier than pasting each day, the two departments generally finish their work at about the same time. Not only does this eliminate the bottleneck, but it increases finished units produced each day by 80 units. All units produced can be sold even though the change increases inventory stock by 10 percent from 200 units. The cost of operating the cutting department two more hours each day is $800. The contribution margin of the finished products is $3 each. Inventory carrying costs are $0.20 per unit per day. What is the change in the daily contribution margin if the change is made?
A) $(396)
B) $(564)
C) $396
D) $400
E) $475
Correct Answer:
Verified
Q120: On-time performance will increase customer satisfaction.
Q124: The Alpha Beta Corporation experiences numerous instances
Q127: Answer the following question(s)using the information below:
The
Q128: Bank of Bowmanville has variable demand for
Q129: The demand for Ballard's Glass Company's products
Q130: Brown Laundry has a variable demand. The
Q130: The objective of the theory of constraints
Q130: What is the cycle time for an
Q133: Answer the following question(s)using the information below:
The
Q139: The theory of constraints describes methods of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents