PERT charts differ from the critical path method in one important way.What is it?
A) PERT charts assign one time to finish each task; CPM does not.
B) PERT charts are based on the use of quality principles; CPM is not.
C) PERT charts assign three time estimates for each activity; CPM does not.
D) PERT charts can be used in service organizations; CPM cannot.
Correct Answer:
Verified
Q63: Which of the following is the streamlining
Q64: Which of the following is a disadvantage
Q71: Which of the following is an important
Q85: Which of the following best describes Six
Q89: Which type of management emphasizes the use
Q91: What does total quality management focus on?
A)
Q94: Which of the following is the technology
Q95: Which of the following systems uses a
Q100: Which of the following is one of
Q108: Which of the following combines computerized manufacturing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents