To complete the first set-up on a new machine took an employee 200 minutes.Using an 80% cumulative average-time learning curve indicates that the second set-up on the new machine is expected to take:
A) 60 minutes.
B) 120 minutes.
C) 80 minutes.
D) 160 minutes.
Correct Answer:
Verified
Q140: A flat or slightly sloped regression line
Q144: It is appropriate to incorporate expected learning-curve
Q146: When new products are introduced, learning-curve effects
Q158: Over the short run,a non-linear cost function
Q159: When using an activity-based costing system,a batch-level
Q160: Choosing an economically plausible cost driver for
Q164: The first set-up on a new machine
Q167: Inflation is a fact,and therefore its influence
Q227: The cumulative average-time learning model with a
Q234: A learning curve is a function that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents