Solved

If Freemantle Engineering Company Has a Safety Stock of 36

Question 73

Multiple Choice

If Freemantle Engineering Company has a safety stock of 36 units of a particular item and the average monthly demand is 270 units,how many days can be covered if the shipment from the supplier is delayed by 12 days? Assume a 360 day year.


A) 8.0 days
B) 12.0 days
C) 4.0 days
D) 6.7 days