Tony placed an order for a customized watch.The customer response time is 36 hours,its receipt time is 8 hours,and manufacturing cycle time is 24 hours.Calculate the delivery time of the product.
A) 12 hours
B) 4 hours
C) 16 hours
D) 2 hours
Correct Answer:
Verified