Ventaz Corp manufactures keyboards.The manufacturing cycle efficiency is 40%.What is its manufacturing time for value added if the manufacturing lead time is 120 minutes per keyboard?
A) 38.50 minutes
B) 60.00 minutes
C) 48.00 minutes
D) 54.00 minutes
Correct Answer:
Verified
Q81: COQ measures such as measures of customer
Q88: Which of the following is an advantage
Q100: Which of the following is true of
Q101: Alex is injured and rushed to Care
Q104: Answer the following questions using the information
Q105: Diane has been asked to consider plans
Q107: Answer the following questions using the information
Q108: Ventaz Corp manufactures glasses.The manufacturing cycle efficiency
Q112: The time from which a machine setup
Q114: The average waiting time is the average