At the Auric Company, the Cost of the Personnel Department

Question 50

Multiple Choice

At the Auric Company, the cost of the personnel department has always been charged to production departments based upon number of employees. Recently, opinions gathered from the department managers indicate that the number of new hires might be a better predictor of personnel costs.
 Total personnel department costs are $287,500 Department ABC Number of employees 70280225 Number of new hires 251312\begin{array}{l}\text { Total personnel department costs are } \$ 287,500 \text {. }\\\begin{array} { l r r r } \text { Department } & \underline { \mathbf { A } } & \underline { \mathbf { B } } & \underline { \mathbf { C } } \\\text { Number of employees } & 70 & 280 & 225 \\\text { Number of new hires } & 25 & 13 & 12\end{array}\end{array}
-If the number of new hires is considered the cost driver,what amount of personnel costs will be allocated to Department A?


A) $35,000
B) $10,667
C) $143,750
D) $43,700

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents