Solved

Given the Partial Project Network Below and the Fact That \ge

Question 23

Essay

Given the partial project network below and the fact that F can be crashed three times if Xt = start time of Activity i, and Yi = amount of crash time used for Activity i.  Given the partial project network below and the fact that F can be crashed three times if X<sub>t</sub> = start time of Activity i, and Y<sub>i</sub> = amount of crash time used for Activity i.    a.Which of the following is correct?  X<sub>F</sub>  \ge X<sub>D</sub> + 10 - Y<sub>D</sub> or X<sub>F</sub>  \ge  X<sub>E</sub> + 10 + Y<sub>E</sub> or Y<sub>D</sub>, Y<sub>E</sub>   \le   0 or X<sub>F</sub> - X<sub>D</sub> - X<sub>E</sub> + 10  \ge  3 b.Which of the following is correct?  y<sub>D</sub>   \le   3 or y<sub>E</sub>   \le   3 or y<sub>F</sub> = y<sub>D</sub> + y<sub>E</sub> or y<sub>F </sub>  \le   3
a.Which of the following is correct?
XF \ge XD + 10 - YD or XF \ge XE + 10 + YE or YD, YE \le 0 or XF - XD - XE + 10 \ge 3
b.Which of the following is correct?
yD \le 3 or yE \le 3 or yF = yD + yE or yF \le 3

Correct Answer:

verifed

Verified

a.XF blured imageX

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents