Metro City and Nu Hi-way Construction Company enter into a construction contract that includes six pages of detailed estimates.Later Metro,whose engineer compiled the figures,discovers that some numbers were added incorrectly,but Nu refuses to make changes.Metro may
A) not rescind the contract.
B) rescind the contract on the basis of fraud.
C) rescind the contract on the basis of mistake.
D) rescind the contract on the basis of economic duress.
Correct Answer:
Verified
Q29: Cooper offers to sell Gable his sport
Q39: Roc buys a farm from Steve,who claims
Q43: Moore Properties, Inc., offers in writing to
Q44: Grover contracts to sell two tracts of
Q45: Olin convinces Pia,who has no artistic ability,that
Q46: Grover contracts to sell two tracts of
Q47: In selling inventory control software to Apex
Q49: Business Investment Company and Chic Properties,Inc.,contract for
Q52: Leyte believes an old comic book he
Q53: At an auction,Vigo bids on an object,believing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents