Activity Z has estimates a = 5,b = 12,m = 7;activity X has estimates a = 5,b = 11,m = 6;and activity Y has estimates a = 3,b = 11,m = 8.Which of the following statements is BEST?
A) Activity X is longer than Activity Y.
B) Activity X has a higher standard deviation than Activity Z.
C) Activity Z is shorter than Activity Y.
D) Activity Y has a smaller variance than Activity Z.
Correct Answer:
Verified
Q25: Project Test Bank is composed of
Q26: At a merge point in a forward
Q27: Project Test Bank is composed of
Q28: The variance of an activity is given
Q29: An activity has a pessimistic time that
Q31: What does a network diagram illustrate and
Q32: An activity has an optimistic time estimate
Q33: Prior to creating a network,it is important
Q34: An activity has an optimistic time estimate
Q35: What are hammock activities and when should
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents