Consider the following two activities: performing warranty work and purchasing components. The warranty work costs $60,000, and the warranty cost of the most efficient competitor is $10,000. Purchasing components costs $100,000 (5,000 purchase orders) . A study reveals that the most efficient level would use 2,500 purchase orders and entail a cost of $55,000. What is the non-value-added cost?
A) $45,000
B) $55,000
C) $60,000
D) $105,000
Correct Answer:
Verified
Q90: A company spends $50,000 a year for
Q91: Using the original design, a machine requires
Q92: Which of the following is NOT a
Q93: What are non-value-added activities?
A) unnecessary inputs
B) valued
Q94: What is a value-added activity?
A) waiting
B) moving
C)
Q96: Sallisaw Savings & Loan
Sallisaw Savings &
Q97: Which term reflects activities that are considered
Q98: Which of the following is NOT a
Q99: Sallisaw Savings & Loan
Sallisaw Savings &
Q100: What is an example of an activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents