On 1 January 2014,Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium.The stadium was to be built over three years,with progress payments as follows: Estimated costs were $50 000 000.The project was 35 per cent complete at the end of 2014,75 per cent complete at the end of 2015 and 100 per cent complete at the end of 2016.Revenues and costs were as estimated.
-How much profit was earned during 2014 if the percentage of completion method was used?
A) $3 281 250
B) $4 200 000
C) $4 900 000
D) $5 600 000
Correct Answer:
Verified
Q21: The profit for a particular project of
Q22: The income statement of Berrima Barbed Wire
Q23: Junction Company had the following transactions,among others,during
Q24: On 1 January 2014,Peter Ltd signed a
Q25: Toy Company manufactures toy koalas.Transactions for the
Q27: On 1 January 2015,Romulus Ltd signed a
Q28: On 1 January 2014,Peter Ltd signed a
Q29: At what point would you expect the
Q30: On 1 January 2015,Romulus Ltd signed a
Q31: At what point would you expect revenue
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents