As part of its quality-improvement program a company is conducting a time study for a particular job.The time study encompassed 10 job cycles,and the results include the following cumulative times and performance rating factors for each element.
The standard time for this job using an allowance factor of 16% is:
A) 1.809 minutes
B) 2.098 minutes
C) 1.530 minutes
D) 2.233 minutes
Correct Answer:
Verified
Q4: As part of a time study a
Q6: How many cycles should be used in
Q6: The allowance factor is a percentage increase
Q7: Workers often do not like to be
Q8: Under normal circumstances and conditions,the time required
Q8: The normal time to perform a job
Q9: Advantages of using a predetermined motion time
Q10: Work sampling tends to be more disruptive
Q15: Rating worker performance is typically an objective,easy
Q17: Determining the length of time it takes
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents