As part of a time study a particular job was analyzed.The study included 20 job cycles and the following cumulative times and performance rating factors for each element were reported:
Assuming an allowance factor of 20% the standard time for this job would be
A) 10.08 minutes
B) 12.10 minutes
C) 14.73 minutes
D) 16.58 minutes
Correct Answer:
Verified
Q2: Work sampling is an easier,cheaper,and quicker approach
Q18: As part of its quality-improvement program a
Q19: Work sampling is a technique for determining
Q21: List the steps in work sampling.
Q22: A work sampling study is being conducted
Q24: How many observations should be taken to
Q25: Management believes a critical piece of equipment
Q25: Briefly discuss the advantages and disadvantages of
Q26: How many cycles should be used in
Q27: For a particular time study a company
Unlock this Answer For Free Now!