Because NPV Is Calculated Using Expected Cash Flows, NPV Is

Question 46

Multiple Choice

Because NPV is calculated using expected cash flows, NPV is ____.


A) generally a correct representation of the future for very risky projects
B) a random variable
C) not subject to the riskiness of the cash flows
D) not subject to the variance of the cash flows

Correct Answer: