The Process of Calculating LS and LF _____________________________

Question 27

Multiple Choice

The process of calculating LS and LF _____________________________.


A) requires only a forward pass through the network
B) requires only a backward pass through the network
C) requires both a forward and backward pass through the network
D) cannot be accomplished until slack is first determined
E) is sufficient for calculating the critical path

Correct Answer:

verifed

Verified