Burkett Company uses a standard cost system. Indirect costs were budgeted at $200,000 plus $15 per direct labour hour. The overhead rate is based on 10,000 hours. Actual results were: Standard direct labour hours 9,000
Actual direct labour hours 10,000
Fixed overhead $190,000
Variable overhead $185,000
The variable overhead efficiency variance was:
A) $10,000 F
B) $50,000 U
C) $35,000 U
D) $15,000 U
Correct Answer:
Verified
Q23: Hyteck, Inc. is a capital intensive firm.
Q24: Hyteck, Inc. is a capital intensive firm.
Q25: Hyteck, Inc. is a capital intensive firm.
Q26: Hogle Mfg. Co. uses a standard costing
Q27: Hogle Mfg. Co. uses a standard costing
Q29: (Appendix 11A)The sales price variance is calculated
Q30: Burkett Company uses a standard cost system.
Q31: Hyteck, Inc. is a capital intensive firm.
Q32: Burkett Company uses a standard cost system.
Q33: Hyteck, Inc. is a capital intensive firm.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents