What cost centers do not have input-output relationships sufficiently well established so that a particular set of inputs will provide a predictable and measurable set of outputs?
A) engineered cost centers.
B) direct cost centers.
C) opportunity cost centers.
D) discretionary cost centers.
Correct Answer:
Verified